Le nouveau pont de Frelighsburg
Photo diary: Frelighsburg's new bridge, Fall 2009.
Click to expand image.
2009/12/10 The bridge is finished!...but still closed to traffic.
2009/11/20 The concrete cures...
2009/11/16 Pouring concrete all day long...
2009/11/13 Main rebar completed...
2009/11/02 Rebar continues...
2009/10/30 Rebar continues...
2009/10/29 Rebar installation continues...
2009/10/27 Formwork and rebar continues...
2009/10/22 South pier formwork... "faux" stone forms...
2009/10/21 South pier formwork...
2009/10/20 North pier formwork begins.
2009/10/19 Temporary steel beams cover the river gap.
2009/10/15 Steel reinforcing bars installed for south footing.
2009/10/14 Concrete is pumped up and over for the south footing base.
2009/10/07 Demolition continues.
2009/10/02
2009/09/29
2009/09/28 The main bridge is closed and demolition begins.
2009/09/25 Preparing for the demolition of the old bridge.
2009/09/23 Temporary footbridge almost ready.
2009/09/18 The temporary footbridge begun.
---
|